Appendix D. Energy & Plant Architecture

v3.2
Cite this section

Copy/paste (plain text):

Jason St George. "Appendix D. Energy & Plant Architecture" in Next Generation Stores of Value: Privacy, Proofs, Compute. Version v3.2. /v/3.2/read/appendix/d-energy-plant/

Energy & Plant Architecture

Plant architecture for verifiable work

Objective: deliver verifiable, dispatchable, and composable power to proving and inference clusters so that proof units and verified FLOPs remain cheap to check and neutral to route.

Electrical topology (MV \to LV):
  • Medium-voltage interconnect with dual utility feeds where available; 2N or N+1 step-down to rack power.

  • UPS/BESS for ride-through and proof-preserving shutdowns.

  • Power-quality SLOs (voltage/frequency/THD) bound worst-case verifier latency inflation.

Thermal topology:
  • Air to liquid (direct-to-chip/immersion) as default for high-density provers.

  • Heat-reuse loops to district heating, greenhouses, or absorption chillers to improve ERE.

  • Publish PUE and ERE: if we monetize heat, ERE <1.0< 1.0 is both possible and economically material.

Network & provenance:
  • Redundant backhaul with clock discipline (PTP/Stratum) so receipts carry tight timing jitter bounds.

  • Facility attestation path: meters and controllers sign energy/thermal telemetry.

Control plane:
  • Workload-aware orchestration couples grid signals \to job scheduler.

  • Interruptible Bronze proofs pause first; Gold proofs ride through with BESS and on-site firming.

Energy procurement & grid posture:
  • Portfolio, not a point bet: long-dated PPAs, nodal index exposure, behind-the-meter firming, and BESS.

  • Co-location with stranded or curtailed energy (hydro spill, wind/solar curtailment, flare-gas).

  • Demand response as a feature: treat prover/inference farms as dispatchable loads.

  • Carbon & provenance: bind certificates into FER format so “kgCO2_2e per proof” is auditable.

SLA tiers that map power quality to receipts:
  • Bronze (interruptible): Shed priority 1. Eligible for demand-response; refunds/penalties via SLA escrow if p95 VerifyPrice breached. Typical use: PoL audits, non-urgent prover workloads.

  • Silver (curtailable with notice): Shed priority 2 with N+1 firming; curtailment windows posted ahead of time. Typical use: batch MatMul-PoUW, rollup proving backlogs.

  • Gold (firm): 2N electrical path or N+1 + BESS ride-through; zero curtailment except force majeure. Typical use: settlement-critical proofs, receipt ledger finalization.

What a lab would need to specify.

The architecture above is a pattern, not a plant. Nothing in this appendix carries a budget, and none should be read into it; the numbers belong to a site study, not a thesis. Before a reference facility can be costed, the following have to be fixed, and the investment addendum (§32: Kardashev Labs: Build and Measure) is where the first of them are:

  • MW scale. The IT load the reference plant is designed for, stated as a range with the prover and verifier shares separated, since verification is threatened by hardware obtainability and proving by bulk power (§14: Layer 0: Verifiable Machines & Energy) and the two do not scale together.

  • PUE and ERE targets. Design-point and worst-season figures for each, with the heat-reuse path that makes ERE <1.0< 1.0 achievable named or the target set above 1.0; both are FER fields (Appendix A: Formal Model of Verification Asymmetry & VerifyPrice) and the targets are what the receipts will be read against.

  • BESS sizing. Energy (MWh) and power (MW) capacity, ride-through duration at Gold load, cycling assumptions, and whether the battery is sized for proof-preserving shutdown only or for firming as well.

  • PPA tenor and structure. Contract length, fixed versus indexed pricing, curtailment terms, and the share of load covered by contract versus nodal exposure; the portfolio posture above becomes a set of instruments only once tenors are chosen.

  • Mapping of SLA tiers to FER/FCR fields. For each of Bronze, Silver, and Gold: which outages entries count as curtailment against the tier, the interconnection class and backup-duration fields of the FCR (§14: Layer 0: Verifiable Machines & Energy) a facility must report to offer the tier, and the SLA-escrow rule that reads them, so that “Gold” is a field-level claim a receipt can falsify rather than a marketing label.

  • Grid and jurisdiction. Balancing authority, interconnection queue position, and the curtailment or rationing posture of the host jurisdiction toward verification workloads, since the last is what Red Line 13 reads.